24 JUL, 2012
"m² AT HIPPODROME" CONSTRUCTION WORKS

The following construction works have been conducted in m² at Hippodrome so far:
Building-1: the roof bars of the third floor have been laid on and the columns are being arranged for the fourth floor;
Building blocks are arranged on the first and the second floors of this building
Building-2: the roof bars of the third floor have been laid on and the building blocks are being arranged on the first floor.
Building-3: The third floor columns and diaphragm are being arranged and the roofing of the third floor will finish by the end of July
Building-4: The foundation plate has been covered with concrete
Building-5: The columns and the diaphragm of the second floor are being armed. 80% of the parking area between the above-mentioned buildings is completed
Building 6: Flooring of the first floor is undergoing
Building 7: The foundation plate and the columns have been completed. The concrete layer will be put on the floor of the first storey till the end of July
Building-9: digging works have been launched and the foundation plate will be laid on till the end of July.